The newest thing on Main Street this month is in the median. The trees that used to line it have been removed, according to the Plymouth DDA's August 2026 status update, and DDA staff were looking at ways to light the median for the holidays. The DDA planned to unveil the new median decor on November 13 at the Salvation Army's Red Kettle Kickoff, which opened the downtown holiday season. The decor is temporary. The trees will be replaced when the streets themselves are rebuilt, as part of a project called DTPForward.
Downtown Plymouth's streets were last redesigned in the mid-1990s. DDA Director Sam Plymale told Hometownlife that only a handful of downtown restaurants stayed open past early evening back then, and that today the number is "closer to 25 or 30." The plan to rebuild the streets for that busier downtown is finished. The DDA board accepted SmithGroup's final DTPForward deliverables by unanimous vote on June 8, 2026. Most of the discussion has been about Kellogg Park, but construction starts a few blocks west of it, on a smaller budget and a much shorter timeline.
Half the money goes to one set of blocks
SmithGroup grouped 17 project areas into six sets. At the DDA's April 2026 meeting, it put the preliminary total at about $40 million, including design, engineering, contingency and construction. The costs are very uneven. Each set is listed below in the order SmithGroup recommended building it.
| Project set | Preliminary estimate, April 2026 | Recommended order |
|---|---|---|
| Set 2: Harvey and Wing Street | about $3.3 million | First, in step with upcoming city infrastructure work |
| Set 1: Main Street and Kellogg Park | about $19.5 million | Grant applications and planning begin right away because of the long lead time |
| Set 5: Fralick and Penniman | about $6 million | Second priority, driven by stormwater needs |
| Set 4: Ann Arbor Trail and Forest | about $8 million | Third priority |
| Set 3: Wing Street East and Deer Street | about $1.7 million | Later |
| Set 6: Union and Church Street | about $1 million | Later |
The Main Street and Kellogg Park set costs almost six times as much as the Harvey and Wing set, and it accounts for about half the plan. SmithGroup called the totals conservative and added a 3% annual escalation for the long term. Every year the Kellogg Park work waits, its price goes up.
Why Harvey and Wing come first
The first set is the one local money can mostly cover. In May, Hometownlife reported that road resurfacing funds were already identified for Harvey and Wing, and that the DDA had money in its fund balance and next budget to help. An August 10 DDA memo said DDA and city administration had discussed two options for 2027 engineering and construction: Project Set 2, or the area near Harvey and Fralick where underground work is needed. Specific funds had not yet been allocated, but the memo said most of that first project was believed fundable through DDA and city money. As of the DDA's November newsletter, construction is expected to begin in 2027 on areas of Harvey Street, with engineering design approvals for the 2027 work expected later this year.
For residents, the change on Harvey is parking. The DTPForward plan adds on-street spaces on Harvey Street between Ann Arbor Trail and Wing. It also adds spaces on two stretches of Main Street, between Penniman and Church and between Ann Arbor Trail and Wing. The plan cuts parking in some places and adds it on streets that have none today. SmithGroup planner Oliver Kiley told Hometownlife the net result could be about 50 to 85 more on-street spaces downtown. The DDA's November 2026 newsletter gives a range of 60 to 80.
Plymale has explained why the work comes in pieces. "Having the entire downtown torn up all at the same time is a nightmare because you're going to lose access to parking areas," he told Hometownlife. He added that working one section at a time lets the city set up detours without cutting off parking access to the whole downtown. The Central Parking Deck is already done. The DDA lists its 2026 renovation as complete and cites an engineer's estimate of about 20 more years of life with regular maintenance. Plans for resurfacing other downtown lots will be addressed as part of the streetscape upgrade.
Kellogg Park waits on grants
The blocks around Kellogg Park are the main reason for the project. They also cost the most and take the longest. Hometownlife described the Set 1 plan this way: fewer traffic lanes in some areas, wider sidewalks, more landscaping and on-street parking, shared-use paths for pedestrians and bicyclists, and curbless, festival-friendly streets with retractable bollards so the city can close streets for events more easily. Kiley told the paper that public comments kept pointing out that the north and south ends of Main Street don't have "the same kind of vibe and feel and energy as the rest of downtown does."
Local money can't cover a project that size. The August memo says Project Set 1 and the $8 million Ann Arbor Trail and Forest set will need significant state and federal grants, and that construction on them isn't expected for several years. Grant deadlines still mean the preparation has to start now. SmithGroup's funding list includes federal Safe Streets for All grants, BUILD grants, Act 51 road funding and renewals of city road bonds. The federal grants follow an 80/20 split, so the local share for Set 1 alone would be about $4 million. Plymale told Hometownlife the DDA could support roughly $400,000 to $500,000 a year through bonding and has been setting money aside to use as a local match.
At its October meeting, the board approved hiring SmithGroup to find and apply for state and federal grants for the bigger phases: Main Street, the area around Kellogg Park, Ann Arbor Trail and Forest Avenue. DDA Deputy Director Reiko Misumi-Schelm has also been taking SEMCOG grant-writing workshops. The 2027 work on the edge of downtown and the grant applications for the core are happening at the same time.
The design around the park can still change
The plan the board accepted in June is a concept, and the board said so when it voted. Director Salloum raised safety concerns about the shared-use path on Main Street and suggested piloting lane reductions and parking changes first. Director Elliott questioned the public feedback on curbless streets but supported the plan as long as engineering revisions are possible. Plymale and SmithGroup confirmed that adjustments are possible. Director Eckley suggested moving the Church Street mid-block crossing to Adams. Director Perry pushed for a walk-your-bike policy inside Kellogg Park, and most of the board agreed.
The public input showed the same split. In SmithGroup's second online survey, mid-block crossings, safety upgrades, gateways and gathering spaces had strong support. Curbless streets got mixed reactions. On parking, respondents 44 and under were more willing to give up spaces for other improvements than respondents 45 and over. At a February open house covered by WXYZ, one resident asked for reworked bike lanes and more parking, and another asked the planners to stay "realistic about the daily needs of the road." Cindy Eckley, owner of Frame Works Plymouth, attended the 1995 streetscape project. She told WXYZ the new design has to look good and also "withstand the test of time."
A resident at the April meeting asked whether curbless streets would hurt drainage. SmithGroup said a properly designed curbless street can increase stormwater capacity. It also described the Main Street path as a low-stress alternative to the current bike lanes. The full list of recommendations also includes pedestrian signals with accessible push buttons and leading pedestrian intervals, street trees, stormwater improvements, gateway markers and new wayfinding signs.
This season's events use the current streets
This year's holiday season runs on the 1990s streets. Santa's City of Plymouth Parade is Friday, November 27. It starts at 6 p.m., stops at 10 city parks and reaches Kellogg Park around 8 p.m. Santa is scheduled to light the park's holiday tree around 8:15 p.m. The Walk of Trees in Kellogg Park also opens that night and stays up through January 4. We covered how neighbors decorate those trees in our Kellogg Park Walk of Trees post. Before the parade, the DDA newsletter lists Pink Friday downtown on November 20, then Small Business Saturday and the Plymouth Community Christmas Farmers Market, 4 to 8 p.m., on November 28.
The DDA has said future DTPForward updates will be part of its Five-Year Action Plan reports at board meetings, which are held the second Monday of each month at 7 p.m. in the City Commission Chambers at Plymouth City Hall. The concept plans and engagement summaries are posted at downtownplymouth.org/dtpforward. Hometownlife's October 2025 preview covers how the planning started. For how these blocks connect to the rest of town, our walk through Old Village picks up north of Kellogg Park, and the Plymouth neighborhood page covers the wider area.